Monday, November 29, 2010
MC 1802 – SOFTWARE PROJECT MANAGEMENT DEC 2009 - previous year anna university questions
MC 1802 – SOFTWARE PROJECT MANAGEMENT MAY 2009 - previous year anna university questions
Tuesday, October 26, 2010
MC 1802-SOFTWARE PROJECT MANAGEMENT DEC 2007
M.C.A DEGREE EXAMINATION NOVEMBER/DECEMBER 2007
5th Semester
MC 1802-SOFTWARE PROJECT MANAGEMENT
(REGULATION 2005)
PART A-(10 x 2=20 marks)
1. What are the differences between ISO 9001 and 9001:2000?
2. What are the quality aspects to be considered to design a Good quality software?
3. What is meant by portfolio?
4. List the goals of a software project.
5. What are the two approaches of determining the effort for the software?
6. Define productivity.
7. How activity sequencing is done?
8. What is project quality??
9. List the steps for quality assurance..
10. Why is the CM process needed in addition to the development process?
PART B-(5 x 16= 80 marks)
11. (a) What is CMM? Explain the CMM framework in detail. Or
(b)Explain the product development lifecycle in detail with illustration.
12. (a)Explain the project selection criteria and the work break down structure.
Or
(b) Explain the process of project planning in detail.
13. (a) Describe the method for the cost estimation and cost budgeting for a
project.
Or
(b) Discuss the various risks in project is susceptible to. How the
Risk Management plans are derived and implemented?
14. (a) Write short notes on:
(i) Brainstorming
(ii) Scheduling
(iii) Human Resource communication in a project.
Or
(b) (i) Consider the following activities from A to J.
Activity Intermediate Duration
Predecessors (month)
A 1
B A 4
C A 2
D A 2
E D 3
F D 3
G E 2
H F,G 1
I C,H 3
J B 2
Construct a CPM network and determine the critical path.
Or
(ii) Consider the following data of the project:
Activity Predecessors Duration
(week)
a m b
A - 1 2 3
B - 2 2 8
C A 6 7 8
D B 1 2 3
E A 1 4 7
F C,D 1 5 9
G C,D,E 1 2 3
H F 1 2 9
Construct the project network and find the following:
(1) Expected duration
(2) Variance of each activity
(3) Critical path
(4) Expected project completion time
15. (a) What is SCM? Explain in detail about SCM lifecycle and requirement
Change management process. (2+14)
Or
(b) (i) Write short notes on Quality function deployment in software
quality assurance. (8)
(ii)Describe the two ways in which system building tools in quality
assurance can optimize the process of building a version of a system
from its components. (8)
MC1802 SOFTWARE PROJECT MANAGEMENT DEC'08
Fifth Semester
MC 1802--SOFTWARE PROJECT MANAGEMENT
Time: Three hours Maximum :100 Marks
Answer ALL questions
PART A--(10 x 2=20 marks)
1. List some of the competencies that contribute to people management skill.
2. What is PM triangle?
3. Give the guiding principles for selecting a project team.
4. List out the project portfolio management model.
5. What are the reasons that make software estimation difficult?
6. List the advantage and disadvantage of using LOC as a unit of measure.
7. What is RAM?
8. Distinguish between hard and soft dependencies.
9. What is software quality assurance?
10. Name some SCM tools.
PART B--(5 x 16=80 marks)
11. (a) Explain the product Development Technique in detail
Or
(b)Explain the following life cycle model in detail.
(i) Waterfall model.
(ii) Prototype model:
12. (a)Describe the steps involved in constructing a work breakdown structure
for a software project with example.
Or
(b) (i) Write short notes on the team formation models
(ii) Explain four models of individual motivation
13. (a) Describe function point analysis in detail. Illustrate with an example.
What is feature point analysis?:
Or
(b) (i) Explain COCOMO regression model in detail
(ii) Give the basic formula's for COCOMO model.
14. (a) Explain the various types of software development dependencies and
Their relationship.
Or
(b) Explain the two methods of scheduling analysis with necessary diagram.
15.(a) Explain the process of building the software quality assurance plan.
Or
(b) What is the basic requirement of SCM system? How to plan and
Organize for an SCM?